日本一卡二卡四卡无卡乱码视频免费,国产女人aaa级久久久级,亚洲国产在一区二区三区,性色av免费网站

泰安揚(yáng)帆數(shù)控科技有限公司為您提供等相關(guān)信息發(fā)布和資訊展示,敬請(qǐng)關(guān)注!
咨詢服務(wù)熱線:
13345281377

新聞資訊

產(chǎn)品

焊接專機(jī)焊接操作時(shí)的十個(gè)要點(diǎn)

來(lái)源:http://niuniury.com/  發(fā)布時(shí)間:2022-11-03 瀏覽次數(shù):0

焊接專機(jī)使用過(guò)程中不允許超載,否則將會(huì)因過(guò)熱而燒毀焊接專機(jī)或造成火災(zāi);超載造成絕緣損壞,還可能引起漏電而發(fā)生觸電事故。下面來(lái)講講山東焊接專機(jī)焊接操作時(shí)的十個(gè)要點(diǎn)。
Overload is not allowed during the use of the special welding machine, otherwise the special welding machine will be burnt or cause fire due to overheating; Overload may cause insulation damage and electric shock due to electric leakage. Now let's talk about the ten key points in the welding operation of Shandong special welding machine.
(1)焊接前,應(yīng)先檢查焊機(jī)設(shè)備和工具是否,如焊機(jī)接地及各接線點(diǎn)接觸是否良好,焊接電纜絕緣外套有無(wú)破損等。
(1) Before welding, check whether the welding machine equipment and tools are safe, such as whether the grounding of the welding machine and the connection points are in good contact, and whether the insulating jacket of the welding cable is damaged.
(2)在設(shè)備上進(jìn)行焊接前,應(yīng)先把設(shè)備的接地或接零線拆掉,焊接完后再恢復(fù)。
(2) Before welding on the equipment, the grounding or neutral line of the equipment shall be removed first and then restored after welding.
(3)進(jìn)行電焊作業(yè)前,應(yīng)檢查作業(yè)環(huán)境,危險(xiǎn)有害因素和設(shè)置監(jiān)護(hù)人員。當(dāng)附近有其他人員和有關(guān)設(shè)施時(shí),應(yīng)采用屏護(hù)和間隔等,保證作業(yè)。需在高處焊接作業(yè)時(shí),須掛好帶。
(3) Before electric welding operation, the operating environment shall be checked, hazardous and harmful factors shall be removed, and supervisors shall be arranged. When there are other personnel and relevant facilities nearby, screen and safety interval shall be adopted to ensure the safety of operation. When welding at heights is required, safety belts must be hung.
(4)更換焊條時(shí),焊工應(yīng)戴絕緣手套。
(4) When replacing welding rods, welders shall wear insulating gloves.
(5)在金屬容器內(nèi)、金屬結(jié)構(gòu)上及其他狹小工作場(chǎng)所焊接時(shí),觸電的危險(xiǎn)性大,須采取專門的防護(hù)措施。如采用墊橡皮墊,戴皮手套,穿絕緣鞋等,以保障焊工身體與焊件間絕緣。禁止使用簡(jiǎn)易無(wú)絕緣外殼的電焊鉗。
(5) When welding in metal containers, metal structures and other narrow workplaces, the risk of electric shock is high, and special protective measures must be taken. For example, rubber pads, leather gloves and insulating shoes are used to ensure the insulation between the welder's body and the weldment. It is prohibited to use simple welding tongs without insulating shell.
山東焊接專機(jī)
(6)改變焊機(jī)接頭,更換焊件需要改接二次回路時(shí),應(yīng)選擇轉(zhuǎn)移工作地點(diǎn)、焊機(jī)檢修暫停工作或下班等,且須切斷電源后方可進(jìn)行操作。
(6) When changing the welding machine joint and changing the weldment, it is necessary to change the secondary circuit, select the transfer work site, suspend the work of the welding machine maintenance or go off work, and cut off the power before operation.
(7)焊機(jī)應(yīng)設(shè)置在防雨和通風(fēng)良好的地方。焊接現(xiàn)場(chǎng)不準(zhǔn)堆放易燃易爆物品。
(7) The welding machine shall be set in a rain proof and well ventilated place. Inflammables and explosives are not allowed to be stacked on the welding site.
(8)交流弧焊機(jī)一次側(cè)電源線須絕緣良好,不得隨地拖拉,長(zhǎng)度應(yīng)不大于5m,進(jìn)線處須設(shè)置防護(hù)罩。
(8) The power line at the primary side of AC arc welding machine must be well insulated, and shall not be dragged anywhere. The length shall not be more than 5m. The incoming line must be provided with a protective cover.
(9)焊機(jī)二次接線宜采用YHS型橡皮護(hù)套、銅芯多股軟電纜,電纜的長(zhǎng)度應(yīng)不大于30m。
(9) YHS type rubber sheath and copper core multi strand flexible cable should be used for the secondary wiring of the welding machine, and the length of the cable should not be more than 30m.
(10)根據(jù)施工需要,焊接專機(jī)宜按區(qū)域或標(biāo)高層集中設(shè)置,并應(yīng)編號(hào)。
(10) According to the construction needs, the special welding machines should be set up in a centralized manner according to the area or standard high level, and should be numbered.
此外布置在室外的焊接專機(jī)應(yīng)設(shè)置在干燥場(chǎng)所,并設(shè)棚遮蔽。且焊接專機(jī)的電源開(kāi)關(guān)應(yīng)單獨(dú)設(shè)置,直流焊接專機(jī)的電源應(yīng)采用啟動(dòng)器控制。更多相關(guān)內(nèi)容就來(lái)我們網(wǎng)站http://niuniury.com咨詢吧!
In addition, the special welding machine arranged outdoors shall be set in a dry place and covered by a shed. The power switch of the special welding machine shall be set separately, and the power supply of the DC welding machine shall be controlled by the starter. More relevant content will come to our website http://niuniury.com Consult!

上一篇:操作自動(dòng)焊接設(shè)備進(jìn)行焊接中的留意事項(xiàng)
下一篇:自動(dòng)焊接設(shè)備的檢查與注意事項(xiàng)

少妇人妻av毛片在线看| 好紧好爽免费午夜视频| 国产无遮挡又黄又爽又色| 亚洲第一页综合图片自拍| 久久国产精品无码一区| 男女18禁啪啪无遮挡激烈网站| 日小骚b少妇真舒服| 99久久国产综合精品五月天喷水| 人人模人人爽人人喊久久| 亚洲综合网国产精品一区| 国产成人a视频高清在线观看| 白丝爆浆18禁一区二区三区| 亚洲AV片不卡无码久久| 国产午夜福利小视频合集| 久久无码专区国产精品| 国产又粗又猛又黄又爽无遮挡| 欧美性xxxxx极品少妇直播| 国产精品无码专区| 成人aaa片一区国产精品| 国产无内肉丝精品视频| 无码一区二区三区在线| 欧美xxxx狂喷水| 国产亚洲精品一二区| 欧美三级乱人伦电影| 亚洲综合色丁香婷婷六月图片| 浪小辉chinese野战做受| 7777奇米四色成人眼影| 久久婷婷丁香五月综合五| 机机对机机无遮挡免费| 欧美xxxxx精品| 伊人色综合久久天天| 色偷偷88888欧美精品久久久| 成在人线AV无码免费| 久久精品国产99久久久古代| аⅴ天堂中文在线网| 97在线视频免费人妻| 国产成人精品A视频一区| 无码人妻熟妇av又粗又大| 妺妺窝人体色www在线小说| 黑人粗长大战亚洲女| 精品国产在天天在线观看|